The City of Moose Jaw has broken ground on a $73-million wastewater headworks facility, the largest infrastructure project in the Saskatchewan city’s history and a major upgrade intended to support population growth while reducing the risk of sewer backups and flooding.
The Crescent View Headworks Facility will replace the existing Crescent View Lift Station, which opened in 1961 and has exceeded its expected 60-year service life. The new facility will be constructed immediately west of the existing station at the east end of Manitoba Street and is expected to be completed by the end of the decade.
Once operational, the new headworks facility will increase wastewater handling capacity to support a population of more than 45,000, with the potential for future expansion to accommodate as many as 60,000 residents.
“Moose Javians may never see this facility, but they will benefit from it every day,” said Moose Jaw Mayor James Murdock in a statement released on October 2. “Every home, business, school, and community facility in Moose Jaw relies on a safe and reliable wastewater system.”
Subscribe to our Newsletter!
The latest environmental engineering news direct to your inbox. You can unsubscribe at any time.
The facility will be constructed above the regional flood elevation and is designed to reduce the risk of sewer backups, overflows and flooding during major storm events.
Major components include high-efficiency pumps and motors, fine screening and grit removal equipment, a septage receiving station, a bulk water fill station and two standby generators. Improved screening will also capture smaller debris that can cause premature wear on pumps and treatment equipment.
The city has budgeted $73 million for the project between 2026 and 2029. More than $9.7 million is being provided through the federal Canada Community-Building Fund, with the remainder funded primarily by the city.

Planning for the project dates back to 2021, when Moose Jaw retained AECOM to undertake conceptual planning and design for the old lift station. An assessment determined that replacing the facility offered better value than rehabilitating the existing infrastructure.
Detailed design advanced through 2022 and 2023, although applications for funding through the Investing in Canada Infrastructure Program and Disaster Mitigation and Adaptation Fund were unsuccessful.
In August 2025, the city secured approximately $9.7 million through the Canada Community-Building Fund, to be allocated to construction over five years beginning in 2026.
Council subsequently approved borrowing $30 million over 15 years in March 2026 to help finance construction. Seven contractors were prequalified for the project before the tendering process ran from March to June.
On July 16, 2026, the city awarded Westridge Construction Ltd. the contract to build the new facility.