Construction of a new water treatment plant at the former Giant Mine near Yellowknife, Northwest Territories, is nearing completion, with the facility expected to begin operations by spring 2027 as part of a major remediation project addressing decades of arsenic contamination.
Aecon is constructing the new water treatment plant, which will process arsenic-contaminated water from underground mine pools and other sources before releasing treated water into Yellowknife Bay.
Construction began in spring 2023, with Parsons serving as the main construction manager for the broader Giant Mine Remediation Project.
The new facility will replace an aging water treatment system dating back to the 1980s, introducing modern treatment technology and monitoring systems designed to meet water quality requirements established by the Mackenzie Valley Land and Water Board.
Subscribe to our Newsletter!
The latest environmental engineering news direct to your inbox. You can unsubscribe at any time.
A primary objective of the plant is to maintain underground mine pool water levels below areas containing arsenic trioxide dust, reducing the risk of contamination.
The facility is designed to reduce arsenic concentrations in treated water to 10 parts per billion, consistent with Health Canada’s drinking water guideline. Real-time sensors will monitor arsenic concentrations, automatically stopping discharges that exceed permitted thresholds and redirecting the water for additional treatment.
Aecon’s scope of work includes drilling deep wells to access underground mine pools, constructing raw and treated water pumping and conveyance systems, and removing contaminated soil.
Unlike the existing treatment system, the new plant will not rely on settling ponds. Instead, treatment residuals will be collected as sludge and disposed of in a specially engineered containment cell within the site’s landfill.
The facility will also use a biomass heating system to reduce greenhouse gas emissions associated with its operation.
Giant Mine operated from 1948 until 2004, leaving behind approximately 237,000 tonnes of arsenic trioxide dust stored underground in five mined-out stopes and 10 purpose-built chambers.
Following an evaluation of potential remediation methods, the federal and Northwest Territories governments selected a strategy involving freezing the arsenic trioxide dust and surrounding rock to prevent contaminants from migrating into the environment.
Maintaining groundwater levels below these underground storage areas is a critical component of the long-term containment strategy, making the new water treatment plant an important part of the site’s remediation infrastructure.
Active remediation work at the site began in 2021 and is scheduled to continue until 2038.